On-site installation requirements rarely fail on commissioning day calibration certificates 1. They fail months earlier. Our Wenzhou team once watched a crated machine sit idle over one undersized air line. Avoidable.
Confirm on-site installation requirements by completing a written site installation condition checklist with your automatic assembly machine supplier before signing the contract. It must specify equipment entry, floor, power, compressed air, environment, interfaces, and commissioning duties, each with measurable values, named owners, deadlines, and test methods.
That checklist is the heart of this article. I will walk through what to prepare, what to ask, what to expect back, and how to keep the final weeks free of disputes.
Last year a cable lug terminal line we built for a German buyer nearly missed its slot. Their facility access dimensions arrived after the frame was welded.
Before contacting your supplier, prepare a factory floor layout with obstacles, door and aisle dimensions, floor load bearing capacity, electrical power supply details, compressed air capacity, environmental data, upstream and downstream interface signals, production part samples, and a list of named internal owners for facilities, controls, quality, and safety.
The best question is not "What does the machine need?" The better question is "What must I provide, what will you install, and how will we both prove it?" Your preparation pack is the starting point for that conversation. In our own projects, we ask every buyer to work through a site installation condition confirmation checklist with us before the contract is signed. It covers equipment entry, installation, power supply, air supply, environment, infrastructure, and commissioning. We do this before signing because changes are cheap on paper and expensive in steel.
These two terms get mixed up. Site requirements are what your building provides: floor, access, utilities, environment, network, and safety. Installation requirements are what happens to the machine once it arrives: unloading, positioning, anchoring, leveling, wiring, plumbing, guarding, and calibration. Commissioning then takes the machine from mechanically complete to safe, repeatable production. If you keep these three buckets separate, the responsibility matrix almost writes itself.
| Item to prepare | What to include | Why it matters |
|---|---|---|
| Factory floor layout | Columns, walls, fire exits, forklift routes 2, pedestrian paths, neighboring machines | A footprint can fit yet still block a maintenance door |
| Facility access dimensions | Dock, door, elevator, aisle, ceiling height, overhead crane rating | Determines shipping module size and rigging plan |
| Floor data | Floor load bearing capacity, concrete thickness, flatness, nearby vibration sources | Feeders and vision systems drift on poor floors |
| Electrical power supply | Voltage, phase, frequency, available current, disconnect location, generator use | Peak servo and heater loads exceed average loads |
| Compressed air | Pressure range, flow reserve, dryer and filtration class, connection point | Pneumatic grippers and blow-offs spike demand |
| Environment | Temperature, humidity, dust, oil mist, lighting, ESD control | Vision and adhesive processes are sensitive |
| Interfaces | Conveyor height, handoff signals, PLC protocol, MES or ERP needs, IT firewall rules | Avoids missing signals at integration |
| Materials | Part drawings, tolerances, sample quantities, packaging, consumables | Commissioning cannot run on unrepresentative parts |
| Material handling equipment | Forklift capacity, crane availability, designated drop site | Reduces handling risk during ingress |
Give the supplier named contacts for project management, facilities, electrical, controls and IT, production, quality, safety, maintenance, and purchasing. We have found that a single missing owner, usually IT, causes more delay than any mechanical problem. Confirm working hours, badges, permits, shutdown windows, and local holidays at the same time.
Every quote we prepare forces a choice: specify utilities tightly now, or keep flexibility while the design evolves. We settle it with staged, controlled revisions.
Confirm power, space, and environmental requirements by requesting measurable utility connection specifications: voltage, phase, frequency, full-load and peak current, pneumatic system pressure and flow, air quality class, floor flatness, anchor layout, maintenance clearance, and ambient temperature, humidity, dust, vibration, and EMI limits, each tied to a test method.
A voltage label on a cabinet is not a specification. The same is true for the phrase "compressed air available." Our rule is simple. Every utility gets a minimum value, a maximum value, a measurement point, a supplier, a deadline, and a test. Here is how we break it down.
Ask for both average and peak consumption. Our bowl feeder assembly lines use servo axes, vibratory drives, and sometimes heaters. When several servos accelerate while a vacuum generator fires, the peak load is far above the running average. Confirm voltage, phase, frequency, allowable variation, full-load current 3, fault current, main disconnect rating, short-circuit protection, grounding and bonding method, and any transformer or UPS need. Request a single-line diagram, terminal schedule, panel heat load, and I/O list before your electrician starts. If you plan backup generator use, say so. Also audit the electromagnetic environment. Nearby induction heaters or welding cells can disturb sensors and vision cameras, so ask the supplier for EMI sensitivity limits.
| Utility | Must be specified as | Common trap |
|---|---|---|
| Compressed air | Pneumatic system pressure range, peak flow, air quality class, dew point, oil-free yes or no, connection size | Pressure drop under peak cycling when multiple grippers fire |
| Vacuum | Vacuum level, flow, response time, filtration, who supplies the pump | Assumed to be included |
| Cooling water | Temperature, flow, pressure, filtration, water quality | Chilled versus process water confusion |
| Exhaust | Flow and duct size for fumes or dust | Heat rejection into the room ignored |
| Network | Drop locations, IP plan, ports, firewall rules | IT arrives last |
We also recommend negotiating utility headroom. Oversized headers and junction boxes cost little during initial installation and support future modular stations later.
Request overall dimensions including doors, cable trays, pneumatic manifolds, and control cabinets. Then request the maintenance envelope: clearance for tooling changes, panel access, feeder bowl removal, and reject-bin handling. Safety clearance zones for light curtains and scanners come from safety-distance calculations, not from guesswork. Ask for anchor type, embedment, spacing, grout or leveling-pad needs, and whether an isolated foundation is required. Our machines ship on adjustable leveling feet or casters, but a level floor still determines final alignment with adjacent conveyors.
Define permissible operating and storage conditions: temperature, humidity, dust, oil mist, corrosive chemicals, lighting for inspection, noise limits, ESD controls, and restrictions on direct sunlight hitting vision stations. A process that passes in our workshop can behave differently on a hotter, dustier floor. If your plant has environmental control systems, share their setpoints and their failure behavior.
Some buyers worry that heavy specification locks them in while the design is still moving. I agree with the risk. The fix is not less specification. The fix is controlled revisions. Freeze the minimum mandatory values at contract, then reissue the sheet at design freeze, pre-shipment, and site-readiness review. Each revision carries a number and a signature.
A US procurement manager once messaged me on WhatsApp: "Does your price include commissioning days?" Fair question. The answer belongs in writing, not chat.
Expect your automatic assembly machine supplier to provide a responsibility matrix, general-arrangement and foundation drawings, electrical and pneumatic schematics, I/O and interface lists, risk assessment, FAT protocol and results, PLC and HMI backups, spare-parts lists, installation and commissioning manuals, defined commissioning days, training, and a site acceptance test protocol.
Support has two halves: people and paper. Both need to be defined before the purchase order is approved, and both should sit in the responsibility matrix. That matrix lists every task with an owner, a due date, the acceptance evidence, and its dependency. Supplier tasks usually include design, drawings, installation instructions, software backups, commissioning labor, training, FAT, and technical support. Customer tasks include floor preparation, electrical service, compressed air, network drops, permits, lifting equipment, production materials, operators, and site access. Third parties such as riggers, electricians, and controls integrators need their own rows. Shared tasks include line integration, risk assessment, SAT, and punch-list closure.
Ask for a document register with revision numbers. At minimum, review approved general-arrangement and foundation drawings, utility specifications, electrical schematics, pneumatic diagrams, parts lists with recommended spares, PLC, HMI, robot, vision, and drive backups with version numbers, network and cybersecurity documentation, the risk assessment 4, maintenance schedules, calibration certificates, FAT protocol and results, installation and commissioning manuals, training materials, and as-built drawings after SAT. For connected machines, we add a cyber-physical handshake document. It states firewall rules, authentication methods, user permissions, time synchronization, and data ownership 5 for MES or ERP links. If your ESG team needs energy and air consumption records, ask for sustainability data hooks such as defined API endpoints or tags, rather than a verbal promise.
| Test | Where | What it proves | Typical scope |
|---|---|---|---|
| FAT | Supplier facility | What the supplier can control | Build against drawings, modes, safety functions, feeders, vision, reject handling, alarms, preliminary throughput, software version |
| SAT | Customer site | What only the site can prove | Shipping damage, alignment, utility values at the connection, grounding, field wiring, I/O, safety after install, dry cycle, first product, throughput, changeover, training |
| Site integration testing | Customer line | Coordinated operation | Handoff timing, permissives, PLC protocol, MES, SCADA, traceability, recipe management |
SAT normally repeats critical FAT tests using real utilities and real parts. It then adds installation, field wiring, integration, and environmental checks.
Buyers often ask us to quote both. Supplier-led installation keeps accountability with the builder and protects machine knowledge, but it costs more and depends on travel schedules. Customer-led installation is cheaper and faster if your technicians are qualified, but it raises the risk of wrong wiring, poor alignment, or undocumented modifications. Our usual compromise: the customer handles rigging, floor, and utility stubs, while our engineer owns anchoring, alignment, power-up, and commissioning. Either way, the contract must state how many commissioning days are included, what happens if the site is not ready, and the daily rate for extra visits.
Faults are isolated at each step. Nothing moves to the next stage until the previous one is signed.
The hardest lesson from our export projects: a short demonstration hides feeder instability. We now insist acceptance metrics are agreed before FAT, never negotiated after installation.
Avoid installation delays and disputes by agreeing measurable acceptance criteria before FAT, requiring a signed pre-installation site readiness report, verifying utilities at the machine connection, running staged commissioning, applying formal change control for any site deviation, and closing a classified punch list with named owners, dates, and payment milestones.
Most disputes trace back to one of three gaps: an unverified site, an undefined metric, or an undocumented change. Each has a direct cure.
Require a pre-installation survey with photographs, measured floor elevations, a floor scan where precision matters, and measured voltage and air pressure at the planned connection points. The survey ends with a signed readiness report. The contract should state who pays if reinforcement or relocation is needed. We have shipped machines against a verbal "the floor is fine" and regretted it. A signed report with numbers removes that argument.
Agree on units per minute, first-pass yield, defect-detection accuracy, machine-attributable reject rate, availability over a defined run, changeover time, maximum manual interventions, and data-reporting accuracy. Then state the window. Instantaneous? One full shift? A longer qualification run? Buyers often push back that a long SAT costs production time. True. But a brief run can hide thermal drift, intermittent network faults, and operator intervention. The compromise we use is a short formal SAT for functional and safety sign-off, followed by a defined production qualification run with clear rules for defects caused by upstream parts. Separate theoretical cycle time from demonstrated sustained throughput, and state whether the quoted rate assumes ideal parts and continuous supply.
A different voltage, a longer cable run, a substitute sensor, or modified guarding must trigger documented change control and a repeat of affected tests. Never waive a changed site condition informally. Safety deserves special care. Confirm the applicable standards, such as local OSHA rules or CE requirements, and validate emergency stops, guards, interlocks, light curtains, safe torque off, and pneumatic energy isolation 6 during the site acceptance test. Decide who handles third-party inspection.
| Defect class | Definition | Production allowed? | Typical payment rule |
|---|---|---|---|
| Critical | Safety or core function fails | No | Milestone withheld |
| Major | Throughput, quality, or integration below criteria | Limited, by written agreement | Partial retention |
| Minor | Cosmetic, documentation, or convenience items | Yes | Small retention until closure |
Record measured utility values, test results, deviations, photographs, open items, owners, and signatures in the SAT record. Fix the warranty start date, final acceptance conditions, required spares, support response times, and remote-access rules in the same document.
Vague on-site installation requirements cost weeks and trust. Confirm every value, owner, test, and signature with your supplier before shipment, and installation becomes routine.
1. European Commission resources for machinery compliance and technical documentation standards. ↩︎
2. Authoritative guide for industrial facility planning and operational space requirements. ↩︎
3. Global authority for international standards governing electrical and electronic technologies. ↩︎
4. Federal safety agency guidelines for identifying and managing industrial workplace hazards. ↩︎
5. Professional association providing standards for industrial automation and data exchange. ↩︎
6. Official ISO standards portal for machinery safety and energy isolation requirements. ↩︎